Tuesday, October 4, 2011

4-10-11 Wilson 8M

Welcome back to Ogi and Dylan.
Adman should be back from the Barrier today...
The team has a goal that must be reached this week.
The inner laminate for the fwd cabin and the foam core must be done by Wednesday night.
Some of the team on the Hull can be spared to work with the Deck team to achieve this.

Inchie, Tiger, William and John however need to keep the Hull fit-out going.
John, water tank.
Tiger, Head area,
William, Companionway door,
Inchie (Yin) Engine box and locker. we have to place a transducer below this area now. Richard will supply.

The EDB430-1270 laminating glass is due to arrive this morning so there isn't any hold up.
Hoff and Lim have cut all the glass we had available for the foredeck lams. While Leon kept going with the foam pre-fitting.
Stephane, Ben, Dylan, Ogi and Leon are all available to get the foam finished.
The edges, where we have the rounded mould are to have the foam core kept back from the edge.  We will secondary bond manually these pieces.
Ogi and Leon are underway getting the edge treatment for the fwd coaming windows foam core.

The substrate surface of the mould has some major contamination. This will need a carefull light sanding before we can wax the surface. Hoff has masked off the flange fwd of the screen area.
The inner laminate must be done today.

Lets keep the shop clean....